Welcome to Official Website of SONEPUR BAZARI AREA of ECL (Eastern Coalfields Limited)

R&R

REHABILITATION

Status of future rehabilitation programmee 10.1.2015

Name of the village and PAFs

No of PAFS

(approx.)

Rehabilitation

site

Expected month of shifting of village

Remark

Bhaluka

182

182

1) Houses construction - 109 families

2) Plots not taken - 73 families

Dahuka

January 2016

Plot has been distributed and 30% resettlement benefit has been paid

Kuchberia

79

79

1) Houses construction - 50 families

2) Plot not taken - 29 families

do

May 2015

Plot has been distributed and 60% resettlement benefit has been paid

Basakdanga - 134

1) Basakdanga - 88 families

2) Nichu Basakdanga - 46 families

134

1) Basahdanga house construction - 57 PAFs

2) Plots not taken - 31 PAFs

1) Nichu Basakdanga - houses construction - 27 PAFs

2) Plots not taken -19 PAFs

do

1) 88 PAFs of Basabdanga - January, 2015

2) Nichu Basabdanga -

May, 2015

do

Bandghat - 74

1) Bandghat - 51

2) Chatimdanga - 23

74

1) Bandghat houses construction - 35 PAFs

2) Plots not taken - 16 PAFs

1) Chatimdanga house construction - 14 PAFs

2) Plots not taken - 9 PAFs

do

Bandghat and Chatimdanga

May, 2015

do

Arsola - 250

1) Arsola - 211

2) Banglapara - 39

250

1) Arsola house construction - 136 PAFs

2) Plots not taken - 75 PAFs

1) Banglapara house construction - 32 PAFs

2) Plots not taken - 7 PAFs

do

201 nos PAFs of village Arsola already shifted and 10 nos PAFs of village Arsola will be shifted within January 2015

39 PAFs of village Bangalapara already shifted.

* 250 no. ST Families already shifted( upto 31.12.2014) and full Resettlement Benefit has been paid (except 500 days MAW) and for remaining families Plot has been distributed and 60% resettlement benefit has been paid.

Sonepur - 900

900

Dahuka

2014-2017

Family survey completed and house survey is going on

Bhatmura - 150

150

To be decided

Within 8 yrs

Rehab. site not finalised

Bazari - 450

450

Bazari Mouza

Within 10 yrs

Rehab. site not finalised

Madhudanga - 400

400

do

Within 5 yrs

do

Nabagram - 800

800

To be decided

After 10 yrs

Rehab. site not finalised

Shankarpur - 250

250

do

 

do

Total — 3669 no families

Total numbers of PAFs to be shifted in future is 3665 approx.

Status of future rehabilitation programmee

Name of the village

No of PAFS

(approx.)

Rehabilitation

site

Proposed year

Of Rehab.

Remark

Bhaluka

178

Dahuka

2014-2015

Plot has been distributed and 30% resettlement benefit has been paid

Kuchberia

79

do

do

do

Basabdanga

134

do

do

do

Bandghat

74

do

do

do

Arsola

250

do

do

29 no. ST Families already shifted and full Resettlement Benefit has been paid (except 500 days MAW) and for remaining families Plot has been distributed and 30% resettlement benefit has been paid.

Sonepur

900

Dahuka

2014-2016

Family survey completed and house survey is going on

Bhatmura

150

To be decided

Within 8 yrs

Rehab.site not finalised

Bazari

450

Bazari mouza

Within 10 yrs

Proposal initiated for Direct Purchase of land of mouza Bazari

Madhudanga

400

do

Within 5 yrs

do

Nabagram

800

To be decided

After 10 yrs

Rehab.site not finalised

Shankarpur

250

do

 

do

Dahuka Rehabilitation Site

  1. Dahuka rehab. Site total land available is 134.18 acres. Out of 134.81 acres 47.12 acres acquired under Direct Purchase and remaining 87.06 acres acquired under LA act. Additional 30 acres will be required for rehabilitation purpose.
  2. Survey work completed, site has been cleaned. Dozing and survey work has been completed of area where Bhaluka,Arsola, Kuchberia, Basabdanga and Bandghat villages will be rehabilitated. In area where Sonepur village will be rehabilitated there are presence of trees planted by ECL. Permission for felling of trees application has been submitted to Ranger Officer, Ukhre Range. After felling of trees site preparation will be started.
  3. Construction of main road and internal road is in progress.
  4. 4 nos wells, 4 nos of tubewell and three nos submersible pumps already installed.
  5. Estimate has been processed for Ponds and shopping complex at Rehab. Site.
  6. Construction of drains and culverts are in progress.
  7. Power line installed at Arsola Rehab.Site and for remaining areas the job is going on.
  8. Estimate is prepared for construction of school building, Temples, ICDS Centers, Boundary wall, Community Hall etc.

Before and after - House at Rehab. site Before and after - House at Rehab. site
Dahuka Rehabilitation site Dahuka Rehabilitation site