REHABILITATION
Status of future rehabilitation programmee 10.1.2015
Name of the village and PAFs |
No of PAFS (approx.) |
Rehabilitation site |
Expected month of shifting of village |
Remark |
Bhaluka 182 |
182 1) Houses construction - 109 families 2) Plots not taken - 73 families |
Dahuka |
January 2016 |
Plot has been distributed and 30% resettlement benefit has been paid |
Kuchberia 79 |
79 1) Houses construction - 50 families 2) Plot not taken - 29 families |
do |
May 2015 |
Plot has been distributed and 60% resettlement benefit has been paid |
Basakdanga - 134 1) Basakdanga - 88 families 2) Nichu Basakdanga - 46 families |
134 1) Basahdanga house construction - 57 PAFs 2) Plots not taken - 31 PAFs 1) Nichu Basakdanga - houses construction - 27 PAFs 2) Plots not taken -19 PAFs |
do |
1) 88 PAFs of Basabdanga - January, 2015 2) Nichu Basabdanga - May, 2015 |
do |
Bandghat - 74 1) Bandghat - 51 2) Chatimdanga - 23 |
74 1) Bandghat houses construction - 35 PAFs 2) Plots not taken - 16 PAFs 1) Chatimdanga house construction - 14 PAFs 2) Plots not taken - 9 PAFs |
do |
Bandghat and Chatimdanga May, 2015 |
do |
Arsola - 250 1) Arsola - 211 2) Banglapara - 39 |
250 1) Arsola house construction - 136 PAFs 2) Plots not taken - 75 PAFs 1) Banglapara house construction - 32 PAFs 2) Plots not taken - 7 PAFs |
do |
201 nos PAFs of village Arsola already shifted and 10 nos PAFs of village Arsola will be shifted within January 2015 39 PAFs of village Bangalapara already shifted. |
* 250 no. ST Families already shifted( upto 31.12.2014) and full Resettlement Benefit has been paid (except 500 days MAW) and for remaining families Plot has been distributed and 60% resettlement benefit has been paid. |
Sonepur - 900 |
900 |
Dahuka |
2014-2017 |
Family survey completed and house survey is going on |
Bhatmura - 150 |
150 |
To be decided |
Within 8 yrs |
Rehab. site not finalised |
Bazari - 450 |
450 |
Bazari Mouza |
Within 10 yrs |
Rehab. site not finalised |
Madhudanga - 400 |
400 |
do |
Within 5 yrs |
do |
Nabagram - 800 |
800 |
To be decided |
After 10 yrs |
Rehab. site not finalised |
Shankarpur - 250 |
250 |
do |
|
do |
Total — 3669 no families
Total numbers of PAFs to be shifted in future is 3665 approx.
Status of future rehabilitation programmee
Name of the village |
No of PAFS (approx.) |
Rehabilitation site |
Proposed year Of Rehab. |
Remark |
Bhaluka |
178 |
Dahuka |
2014-2015 |
Plot has been distributed and 30% resettlement benefit has been paid |
Kuchberia |
79 |
do |
do |
do |
Basabdanga |
134 |
do |
do |
do |
Bandghat |
74 |
do |
do |
do |
Arsola |
250 |
do |
do |
29 no. ST Families already shifted and full Resettlement Benefit has been paid (except 500 days MAW) and for remaining families Plot has been distributed and 30% resettlement benefit has been paid. |
Sonepur |
900 |
Dahuka |
2014-2016 |
Family survey completed and house survey is going on |
Bhatmura |
150 |
To be decided |
Within 8 yrs |
Rehab.site not finalised |
Bazari |
450 |
Bazari mouza |
Within 10 yrs |
Proposal initiated for Direct Purchase of land of mouza Bazari |
Madhudanga |
400 |
do |
Within 5 yrs |
do |
Nabagram |
800 |
To be decided |
After 10 yrs |
Rehab.site not finalised |
Shankarpur |
250 |
do |
|
do |
Dahuka Rehabilitation Site
- Dahuka rehab. Site total land available is 134.18 acres. Out of 134.81 acres 47.12 acres acquired under Direct Purchase and remaining 87.06 acres acquired under LA act. Additional 30 acres will be required for rehabilitation purpose.
- Survey work completed, site has been cleaned. Dozing and survey work has been completed of area where Bhaluka,Arsola, Kuchberia, Basabdanga and Bandghat villages will be rehabilitated. In area where Sonepur village will be rehabilitated there are presence of trees planted by ECL. Permission for felling of trees application has been submitted to Ranger Officer, Ukhre Range. After felling of trees site preparation will be started.
- Construction of main road and internal road is in progress.
- 4 nos wells, 4 nos of tubewell and three nos submersible pumps already installed.
- Estimate has been processed for Ponds and shopping complex at Rehab. Site.
- Construction of drains and culverts are in progress.
- Power line installed at Arsola Rehab.Site and for remaining areas the job is going on.
- Estimate is prepared for construction of school building, Temples, ICDS Centers, Boundary wall, Community Hall etc.
Before and after - House at Rehab. site | Before and after - House at Rehab. site |
Dahuka Rehabilitation site | Dahuka Rehabilitation site |